• Today: October 31, 2025

ganga-saran-v-firm-ram-charan-ram-gopal-frustration-of-contract

31 October, 2025
2601
Ganga Saran v. Firm Ram Charan Ram Gopal (1952) — Frustration of Contract | The Law Easy

Ganga Saran v. Firm Ram Charan Ram Gopal (1952) — Frustration of Contract

Court: Supreme Court of India Year: 1952 Citation: AIR 1952 SC 9 Area: Contract — Frustration (S.56) Reading time: ~6 min

Author: Gulzar Hashmi Location: India Publish Date: 26 Oct 2025

PRIMARY_KEYWORDS: frustration of contract, Section 56, AIR 1952 SC 9 SECONDARY_KEYWORDS: supervening impossibility, default, cloth supply, settlement for 61 bales
Hero image: frustration of contract in cloth supply dispute

Quick Summary

There were five cloth supply contracts in April 1941. After disputes, the parties settled: the seller would deliver 61 bales by 17 Nov 1941. No delivery came. The buyer warned and then sued for the market loss. The seller said, “It became impossible” and argued frustration. The Supreme Court disagreed: the case showed default, not a true supervening impossibility. Frustration could not rescue the party in default.

Issues

  • Do the facts justify applying the doctrine of frustration of contract?
  • Was non-performance due to a supervening event, or due to the seller’s own default?

Rules

  • Frustration (Section 56, ICA): Contracts are discharged only when performance becomes impossible or unlawful due to a supervening event beyond control.
  • No Self-Created Impossibility: The doctrine does not help a party whose own default caused the failure.
  • Not a Contingency: If the promise was absolute (not dependent on an uncertain event), non-delivery is a breach, not frustration.

Facts (Timeline)

10–18 Apr 1941: Five contracts for cloth from New Victoria Mills (Kanpur) & Raza Textile Mills (Rampur).
By Oct 1941: Only 11 bales taken; disputes continued.
17 Oct 1941: Settlement: seller to deliver 61 bales by 17 Nov 1941.
20 Nov 1941: Buyer sends telegram: deliver through bank within 3 days or we sue.
No Reply/No Delivery: Seller stays silent; no goods arrive.
23 Apr 1942: Suit filed for ₹9,808 as loss due to market rise.
Defence: “Performance became impossible”—claiming frustration.
Timeline: contracts, settlement for 61 bales, warning telegram, suit for loss

Arguments

Appellant (Buyer)

  • Promise to deliver 61 bales by a fixed date was absolute.
  • No unforeseen event made performance impossible; seller simply defaulted.
  • Market rose; loss should be compensated as damages for breach.

Respondent (Seller)

  • Said performance became impossible; mills/conditions made supply impracticable.
  • Tried to rely on frustration to be discharged from liability.

Judgment

Appeal allowed. The Supreme Court held for the buyer. The contract, as settled, required delivery by a fixed date and was not contingent on any uncertain event. The seller did not prove a genuine supervening impossibility beyond control. Because the failure was attributable to the seller’s side, the doctrine of frustration did not apply. Damages were therefore payable.

Judgment graphic: frustration rejected where default caused non-performance

Ratio Decidendi

Frustration discharges only when a supervening event, not caused by the parties, makes performance impossible or unlawful. If non-performance results from the promisor’s own default or matters under their control, frustration is unavailable.

Why It Matters

  • Draws a clear line between breach and true frustration.
  • Warns sellers: supply risks you can control won’t be excused.
  • Useful for exams on Section 56 and post-settlement obligations.

Key Takeaways

Absolute Promise: Fixed date delivery ≠ contingent promise.
No Excuse for Default: Self-caused non-performance ≠ frustration.
Damages Follow: Market rise loss can be claimed on breach.
Do Avoid
Document supervening events beyond control if they occur.Labeling supply difficulties as “impossible” without proof.
Allocate supply risks expressly in contracts.Relying on mills/permits unless made express conditions.
Use clear contingencies when performance depends on third parties.Assuming post-settlement promises are conditional.

Mnemonic + 3-Step Hook

Mnemonic: “NO FAULT → FRUSTRATION; YOUR FAULT → COMPENSATION.”

  1. Spot the Event: Was there a supervening, uncontrollable event?
  2. Check Control: If caused by promisor/default → no frustration.
  3. Apply S.56: True impossibility discharges; otherwise damages.

IRAC Outline

Issue

Does the doctrine of frustration excuse the seller from delivering 61 bales by 17 Nov 1941?

Rule

Frustration applies only for supervening impossibility beyond control; it cannot be invoked where the promisor’s own default caused the failure.

Application

The promise to deliver was unconditional; no proven external event made performance impossible. The record showed default, not frustration. Hence, Section 56 did not discharge the contract.

Conclusion

Frustration rejected; buyer entitled to damages for non-delivery.

Glossary

Frustration
Discharge of a contract due to supervening impossibility or illegality beyond parties’ control.
Supervening Event
An unforeseen post-contract event that makes performance impossible in law or fact.
Contingent Contract
One that depends on a future uncertain event; if not stipulated, promise is absolute.

FAQs

No. The settlement set a fixed delivery date. Without an express contingency, the promise remained absolute.

When a later, uncontrollable event makes performance impossible or unlawful—e.g., destruction of subject matter, legal ban.

The seller. Because the promise was unconditional and no true supervening event was proved.

Damages for market loss due to non-delivery—calculated from the rise in market price over contract price.
Reviewed by The Law Easy Category: Contract Frustration Case Brief
```

Comment

Nothing for now