• Today: January 10, 2026

Garware Wall Ropes Ltd. v. Coastal Marine Constructions and Engineering Ltd.

04 November, 2025
7201
Garware Wall Ropes Ltd v. Coastal Marine Constructions & Engineering Ltd (2019) — Unstamped Arbitration Agreement

Garware Wall Ropes Ltd. v. Coastal Marine Constructions & Engineering Ltd.

Easy-English explainer on unstamped contracts and the enforceability of arbitration clauses under the Stamp Act & Arbitration Act.

Supreme Court of India 2019 (2019) 9 SCC 209 Arbitration / Stamp Act ~7 min read India
Author: Gulzar Hashmi Published:
Courtroom-Stamp Act theme for Garware Wall Ropes case

Quick Summary

(2019) 9 SCC 209

The Supreme Court ruled that an arbitration agreement inside an unstamped contract is not enforceable. Before appointing an arbitrator under Section 11, the court must ensure the document is duly stamped. If not, it must be impounded and stamping deficiencies with penalty must be paid first.

Issues

  • Can an arbitration agreement in an unstamped document be enforced?

Rules

  • Severability is recognized, but stamping affects enforceability of the clause housed in the document.
  • If the contract is unstamped, the arbitration clause cannot be treated as an independent agreement for enforcement.
  • Court must impound the document; only after deficit duty and penalty are paid can the matter proceed.

Facts (Timeline)

Timeline of Garware Wall Ropes arbitration dispute
Sub-contract executed: It contains an arbitration clause.
Dispute arises: Respondent invokes arbitration and appoints an arbitrator.
Objection raised: Appellant challenges appointment.
Section 11 motion: Respondent moves court for appointment of arbitrator.
Stamping defect found: Sub-contract is unstamped under the Stamp Act.

Arguments

Appellant

  • Unstamped contract cannot be acted upon; clause within is unenforceable.
  • Document must be impounded first as per Stamp Act.

Respondent

  • Severability keeps the arbitration clause alive.
  • Prayer for appointment under Section 11 should be allowed despite stamping issue.

Judgment

Judgment illustration for Garware Wall Ropes

The Supreme Court set aside the Bombay High Court. It held that an arbitration agreement in an unstamped document cannot be invoked. The court must first impound the document; after deficit duty and penalty are paid, the arbitration clause may be acted upon.

Ratio Decidendi

Severability does not bypass stamping. While conceptually separate, an arbitration clause embedded in an unstamped contract is not enforceable until the Stamp Act is satisfied.

Why It Matters

  • Places a compliance checkpoint (stamping) before Section 11 appointments.
  • Guides drafting and execution practices—stamp first, arbitrate later.
  • Clarifies limits of the severability doctrine under Indian stamping law.

Key Takeaways

  1. Unstamped contract → arbitration clause not enforceable yet.
  2. Court must impound and collect duty & penalty first.
  3. Severability does not override Stamp Act compliance.

Mnemonic + 3-Step Hook

Mnemonic: “STAMP → STAND → SEND”

  • STAMP the contract (cure deficit + penalty).
  • STAND the clause becomes enforceable.
  • SEND to arbitration (Section 11 may proceed).

IRAC Outline

Issue: Enforceability of arbitration clause in an unstamped contract.

Rule: Severability recognized, but Stamp Act compliance is prerequisite to enforcement.

Application: Contract was unstamped; clause could not be invoked; document had to be impounded first.

Conclusion: Appointment of arbitrator cannot proceed until stamping defects are cured.

Glossary

Severability
Arbitration clause is conceptually separate from the main contract.
Impounding
Court seizes an insufficiently stamped document until duties/penalties are paid.
Section 11 (A&C Act)
Court’s power to appoint arbitrators.

Student FAQs

Not dead, but unenforceable until stamping dues and penalty are paid.

No. Stamping must be addressed before Section 11 appointment proceeds.

Severability is acknowledged, but stamping compliance controls enforceability.

Comment

Nothing for now