• Today: January 09, 2026

Welspun Specialty Solutions Limited v. ONGC (2021)

01 January, 1970
9001
Welspun Specialty Solutions Ltd v. ONGC (2021) — Time not the Essence | The Law Easy

Welspun Specialty Solutions Limited v. ONGC (2021)

Supreme Court of India Year: 2021 Bench: Justice N. V. Ramana & Justice Surya Kant Area: Contract & Arbitration Reading Time: ~7 min India
Author: Gulzar Hashmi  ·  Published:
Welspun v. ONGC Supreme Court case - hero image

Quick Summary

The Supreme Court clarified when “time is the essence” in commercial contracts. Despite a clause calling time essential, the extensions granted and the conduct of parties showed that strict timelines were not central here.

  • Time was not the essence for ONGC’s pipe supply orders.
  • Liquidated damages could not apply; only proven actual loss was recoverable.
  • Arbitral Tribunal’s plausible view restored; High Court interference under Sections 34 & 37 was unwarranted.
```

Issues

  1. Should the arbitral award be set aside under Section 34 of the Arbitration and Conciliation Act, 1996?
  2. Was time the essence of the supply contract, allowing ONGC to levy liquidated damages?

Rules

  • Whether time is essential is judged from the whole contract and parties’ conduct, not a single clause.
  • Extensions and waiver clauses can dilute strict timelines.
  • Where time is not essential, liquidated damages do not automatically follow; the promisee must prove actual loss.
  • Under Sections 34/37, courts do not re-appreciate a tribunal’s plausible interpretation.

Facts (Timeline)

Case facts timeline visual for Welspun v. ONGC
Global Tender: ONGC sought 3,93,297 m of seamless steel casing pipes.
Bidder: Remi Metals (now Welspun) won; proposed supply via Volski Tube Mills, Russia.
Purchase Orders: POs 275, 276, 277, 286; delivery within 40 weeks; clause said time is essence; LD @ 0.5%/week up to 5%.
Delays & Extensions: Performance delays occurred; ONGC granted extensions, sometimes without LD.
Deductions: ONGC deducted USD 8,07,804.03 + ₹1,05,367 as LD from bills; supplier disputed and raised further claims.
Arbitration: Tribunal held time was not essence; allowed only actual loss (₹3,80,64,830), excluding waived periods.
Litigation: District Court broadly upheld; Uttarakhand High Court reversed, holding time was essence.
Appeals: Both sides approached the Supreme Court.

Arguments

Appellant (Welspun)

  • Extensions and waiver showed time was not essential.
  • LD cannot apply after waiver; only actual loss is recoverable.
  • Tribunal’s view was reasonable; High Court overstepped Sec. 34/37.

Respondent (ONGC)

  • Contract expressly said time is essence; LD clause must operate.
  • Delays hurt project schedules; supplier should bear LD.
  • High Court rightly corrected tribunal’s error.

Judgment

Supreme Court judgment graphic for Welspun v. ONGC

The Supreme Court restored the arbitral award. It held that, in this contract, time was not the essence, mainly due to the extension mechanisms and the parties’ behavior. Therefore, ONGC could not levy LD for periods it had effectively waived. Only actual damages proven on evidence were permissible.

  • High Court’s interference under Sections 34/37 was improper.
  • Welspun’s appeals allowed; ONGC’s appeal dismissed.

Ratio

A clause stating “time is essence” is not conclusive. Courts look at the entire contract and conduct. Extension and waiver provisions signal that strict time is not central. Where time is not of the essence, LD does not automatically apply; the claimant must prove real loss.

Appellate courts should not replace a tribunal’s reasonable reading with their own.

Why It Matters

  • Drafting Tip: If time truly matters, avoid broad, repeated extensions without LD.
  • Claims Strategy: Track actual loss evidence if LD may not stick.
  • Arbitration Law: Respect the tribunal’s plausible view; courts have a limited correction role.

Key Takeaways

  • “Time is essence” needs support from conduct and structure, not only words.
  • Granting extensions often waives strictness about time.
  • Without essence, LD turns into a proof of loss exercise.
  • Section 34 is not a rehearing: plausible tribunal views stand.

Mnemonic + 3-Step Hook

Mnemonic: T-E-ATime clause, Extensions, Actual loss.

  1. Read the contract (is time clause backed by structure?).
  2. Check conduct (extensions/waiver show non-essence?).
  3. Assess damages (LD or prove actual loss?).

IRAC Outline

Issue: Was time the essence; can LD be imposed; can award be set aside under Sec. 34?

Rule: Whole-contract test; conduct matters; extensions dilute essence; LD needs essence or proof of loss; limited court review.

Application: Multiple extensions and waiver language showed non-essence; ONGC must prove actual loss; tribunal’s reading was plausible.

Conclusion: Time not essence; LD disallowed for waived periods; arbitral award restored.

Glossary

Essence of Contract
A term so central that breach of timing lets the other side end the contract or claim LD.
Liquidated Damages (LD)
A pre-agreed sum payable on breach, used if time is truly essential.
Waiver
When a party voluntarily gives up a right (e.g., strict timelines by granting extensions).

FAQs

Time was not the essence; LD not payable for waived periods; only actual loss proved by ONGC could be recovered; arbitral award restored.

No. Courts read the whole contract and conduct. Extension and waiver terms may show time is not central.

If timing is critical, keep extension rights narrow and make consequences clear; avoid behavior that suggests waiver.

Limited. Courts do not re-evaluate evidence if the tribunal’s view is reasonable and not illegal or perverse.

Reviewed by The Law Easy

Indian Contract Act, 1872 (ICA) Arbitration Time as Essence Liquidated Damages

Comment

Nothing for now