• Today: January 09, 2026

Shripati Lakhu Mane v. The Member Secretary, Maharashtra Water Supply and Sewerage Board

01 January, 1970
6051
Shripati Lakhu Mane v. Member Secretary, MWSSB — Abandonment vs Breach (Sec 67 ICA) | The Law Easy

Shripati Lakhu Mane v. The Member Secretary, Maharashtra Water Supply and Sewerage Board

Indian Contract Act, 1872 Section 67 Supreme Court of India India ≈6 min read
Author: Gulzar Hashmi Published: Tags: ICA 1872, Section 67, Abandonment, Breach, Reciprocal Promises
Supreme Court theme with contract icons for Section 67 ICA
```
```

Quick Summary

The Supreme Court drew a clean line between abandonment and breach. A party may abandon a right, but cannot abandon an obligation. If a contractor stops work until the other side performs its reciprocal promises, that stance is not abandonment. It may amount to breach or be excused under Section 67, ICA when the promisee’s neglect blocks performance.

```

Issues

  • Did the contractor abandon the contract, or was it a refusal linked to reciprocal promises?

Rules

  • Section 67, ICA: If the promisee neglects or refuses to give reasonable facilities, the promisor is excused for the non-performance caused by that neglect.
  • Material changes to the original contract allow a party to refuse to perform those original terms; this does not become abandonment.
  • Abandonment concerns rights (waiver). Refusal to perform an obligation amounts to breach, not abandonment.
  • On refusal, the other party may sue for breach or rescind and claim quantum meruit for work already done.
ICA 1872 Sec 67

Facts (Timeline)

Timeline graphic of work order, stoppage, and court stages
03 Jul 1986: Registered contractor received work order for a water supply scheme in Ratnagiri; completion time: 30 months.
28 Jul 1986: Respondents put the work in abeyance; after representation, they told the contractor to start on 17 Dec 1986.
Contractor flagged non-availability of specified pipes; when different pipe sizes were proposed, the contractor sought fresh rates.
02 Mar 1987: Respondents ordered pipeline work to stop and asked to start at another location; scheme saw modifications.
Contractor said completion was blocked by funding issues and delay in sanctioning modified rates; a fine of ₹10/day was imposed to push restart.
Trial Court: Decreed recovery partly—₹24,97,077 with interest (from a claim of ₹51,35,289).
High Court: Reduced to ₹7,19,412 on the ground of abandonment by the contractor.
Supreme Court: Appeal filed challenging the High Court’s finding of abandonment.

Arguments

Appellant / Contractor

  • Work was stalled by changes, lack of specified materials, and delayed revised rates.
  • Refusal to continue without reciprocal performance is justified; not abandonment.
  • Section 67 excused non-performance caused by the respondents’ neglect.

Respondents / Board

  • Contractor’s stoppage amounted to abandonment of the project.
  • Penalties were proper, and the decree had to be reduced to reflect abandonment.
  • Scheme changes did not excuse the contractor’s obligations.

Judgment

Judgment gavel for Supreme Court decision
  • Refusal to perform an obligation is a breach, not abandonment.
  • Stopping work until reciprocal promises are met cannot be tagged as abandonment.
  • Section 67 protects a promisor when the promisee’s neglect blocks performance.
  • The High Court erred in overturning the Trial Court; its view on abandonment was incorrect.

Ratio

Abandonment relates to rights. A contractor’s refusal to continue work due to unperformed reciprocal promises is not abandonment. Under Section 67, ICA, neglect by the promisee excuses non-performance to that extent.

Why It Matters

  • Clarifies the difference between abandonment and breach in construction contracts.
  • Strengthens the role of Section 67 where employer actions hinder performance.
  • Guides contractors on lawful responses when terms are materially changed mid-project.

Key Takeaways

Rights vs Duties

You can waive a right; you cannot abandon an obligation.

Section 67 Shield

Promisee’s neglect can excuse non-performance by the promisor.

Reciprocal Promises

Stopping work pending reciprocity ≠ abandonment.

Document Changes

Record material changes and rate revisions to avoid disputes.

Mnemonic + 3-Step Hook

Mnemonic: “RIGHTS CAN REST; DUTIES CAN’T.”

  • Abandon rights → possible.
  • Abandon obligations → no; it’s breach.
  • Sec 67 → neglect by promisee can excuse performance.

3-Step Hook:

  1. Ask: “Right or obligation?”
  2. Check: any neglect/material change by promisee?
  3. Decide: breach/quantum meruit; not abandonment.

IRAC Outline

Issue

Was the contractor’s refusal abandonment or a response to unmet reciprocal promises?

Rule

Sec 67 ICA; abandonment concerns rights; refusal of obligation → breach, not abandonment.

Application

Material changes, delayed rates, and neglect hindered performance; contractor’s stance was not abandonment.

Conclusion

High Court erred; Trial Court view substantially restored; no abandonment.

Glossary

Abandonment
Giving up a right; not the same as refusing to perform an obligation.
Breach
Failure to perform a contractual duty without legal excuse.
Section 67, ICA
Promisee’s neglect can excuse the promisor’s non-performance to that extent.
Quantum Meruit
Payment for the value of work done when a contract is rescinded or otherwise ends.

FAQs

No. If refusal is tied to unmet reciprocal promises, it is not abandonment; it may be breach or excused by Section 67.

Material alteration lets the contractor refuse the original terms. That refusal is not abandonment.

If the employer’s neglect prevents performance, the contractor is excused for the non-performance caused by that neglect.

The innocent party may sue for breach or rescind and claim quantum meruit for the value of work already done.
```

Comment

Nothing for now